Project manage your own kitchen refurbishment

a step-by-step guide that will help you save thousands on your install.

Project Manager Duties
PLANNING YOUR BUILD
easy Decide what you will do with your old kitchen (skip, local dump, re-sell Online). Plan how you will cook while your kitchen is out of action.
challenge Get your plans designed and have all main kitchen components delivered to your property incl: Units, Worktops, Sink, Taps, Appliances, Lighting, Flooring, Splashback Tiles. For glass splashbacks, wait until units are installed.
1. GET YOUR PLANS MADE
You can either get a retailer like Wren or Magnet to draw you up some plans, or use an online tool like the one Ikea has to draw your new kitchen layout.
Make sure to mark any new electrics you want incl. sockets, down lights, under-counter LED lighting.
Guide below is based on a small / medium sized kitchen.

Project Manager Duties
PREP FOR STAGE 2
easy Find a Plumber in prep for stage 2 (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your plumber requires any materials for first-fix plumbing, and get them ordered.

2. REMOVE OLD KITCHEN
Plumber on day rate2 days
Remove entire kitchen (including floor if you wish to replace). Install water, waste and radiator pipes to match the locations in your new kitchen plan.

Gas hob and boiler replacement (1)
If you have gas and are moving the location of your hob, or replacing your boiler, this is the stage you will want to find a Gas Engineer on Subbies and ask them to move the pipework to the locations shown in your new kitchen plan.
Project Manager Duties
PREP FOR STAGE 3
easy Find an Electrician in prep for stage 3 (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your electrician requires any materials for first-fix electrics, and get them ordered.

3. INSTALL NEW CABLES
Electrician on day rate1 day
Install first-fix cables for sockets, lights extractor fan, and appliances to match locations in the the new kitchen plan you had made.

Project Manager Duties
PREP FOR STAGE 4
easy Find a Plasterer in prep for stage 4 (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your plasterer requires any materials, and get them ordered.

4. PLASTERING
Plasterer on day rate1 day
Skim kitchen walls (and ceiling if required).

Project Manager Duties
PREP FOR STAGE 5
easy Find a Decorator in prep for stage 5 (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your Decorator requires any materials, and get them ordered.
challengeIf you are installing glass splashbacks, now is the time to measure up the sizes and get them ordered.

5. DECORATING
Decorator on day rate2 days
Decorate kitchen using paint you have chosen.

Project Manager Duties
PREP FOR STAGE 6
easy Find a Carpenter for wood floor, or Tiler for tiled floor (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your floor fitter requires any materials, and get them ordered.

6. NEW FLOOR (if replacing)
Carpenter or Tiler on day rate2 days
Install new floor. Use a carpenter for wooden floors or a tiler if you are having tiles or flagstones.

Project Manager Duties
PREP FOR STAGE 7
very easy Find a Carpenter in prep for stage 7 (or use the same Carpenter you used in stage 5). Text some photos of your job and kitchen plan you had made. Ask if your Carpenter requires any materials, and get them ordered.

7. KITCHEN FITTING
Carpenter on day rate3 days
Build and install new units, worktops and sink basin.

Gas hob and boiler replacement (2)
This is the stage you will want to find a Gas Engineer on Subbies and ask them to connect your gas hob, and replace your boiler if it is part of your project.
Project Manager Duties
PREP FOR STAGE 8
easy Find a Tiler in prep for stage 8 (five minute job on Subbies). Text some photos of your job and kitchen plan you had made. Ask if your Tiler requires any materials, and get them ordered.

8. INSTALL SPLASHBACKS
Tiler on day rateTiles 2 daysGlass 1 day
Install your kitchen splashback tiling, or glass splashbacks, whichever you have chosen to use.

Project Manager Duties
PREP FOR STAGE 9
very easy Find an Electrician in prep for stage 9 (or use the same Electrician you used in stage 3). Text some photos of your job and kitchen plan you had made. Ask if your Electrician requires any materials, and get them ordered.

9. FINAL ELECTRICS
Electrician on day rate1 day
Install second-fix electrics. Lights, sockets, extractor fan, and all electric appliances (oven, hob, fridge, microwave etc.).

Project Manager Duties
PREP FOR STAGE 10
very easy Find a Plumber in prep for stage 10 (or use the same Plumber you used in stage 2). Text some photos of your job and kitchen plan you had made. Ask if your Plumber requires any materials, and get them ordered.

10. FINAL PLUMBING
Plumber on day rate1/2 day
Connect taps, hook up washing machine, dishwasher, radiators, and test after install.